What a difference a day makes – The Technology and Construction Court provides guidance on calculating notice periods under JCT
April 25, 2023
What a difference a day makes – The Technology and Construction Court provides guidance on calculating notice periods under JCTApril 25, 2023 In Elements (Europe) Limited V FK Building Limited1 newly appointed Technology and Construction Court (“TCC”) Judge, Mr Justice Constable, considered the payment application notice provisions in a Joint Contracts Tribunal (“JCT”) sub-contract and held that; a “day” is not the same as a “clear day” and if a contract specifies a day for performance of an obligation, then the party performing the obligation has until the end of that day. The Court also gave guidance on when it was appropriate for parallel Part 8 proceedings to be heard, that may affect the enforceability of an adjudication award. BackgroundThe defendant, FK Building Limited (“FK”) was a main contractor who engaged the claimant, Elements (Europe) Limited (“Elements”), to carry out remedial works at an apartment block in Salford under a JCT Standard Building Sub-Contract Conditions SBCSub/C 2016 Edition with bespoke amendments (the “Sub-Contract”). Elements brought an application for summary judgment to enforce an adjudicator’s decision against FK following a payment dispute. FK made a tandem Part 8 application relating to the validity of the payment application which was the subject matter of the payment dispute. FK argued that the application was invalid because it was received late and therefore it would be unconscionable for the Courts to enforce the decision. The Sub-ContractThe Sub-Contract terms provided that Elements could make a payment application in respect of an interim payment: “4.6.3.1. so as to be received not later than 4 days prior to the Interim Valuation Date for the relevant payment…” The relevant interim valuation date was 25 October 2022 and the parties agreed that Elements emailed the payment application to FK on 21 October 2022 at 22:07, and this was received by FK between 22:07 and 22:08 on the same day. However, FK contended that the meaning of clause 4.6.3.1 of the Sub-Contract was that the application:
Findings of the CourtThe Court held that the meaning of a “day” was different to “clear days” because words will be construed according to their natural language and usage. As clause 4.6.3.1 did not refer to “clear days” then the parties did not mean clear days – therefore, the 21 October was the correct date, being four days prior to 25 October. With regard to the timing of the application, the Court confirmed that the law does not deal in fractions of a day – if a contract specifies a day for performance of an obligation, then the party performing the obligation has until the end of that day. Whilst the parties could agree a specific time in their contract for service, this had not been done in the Sub-Contract. The site working hours in the specification were not relevant to the meaning of “days” in clause 4.6.3.1. Despite FK arguing that it was commercially unworkable and unbusinesslike to serve a notice so late in the day, the Court held that it actually provided certainty for the parties to know that receipt could take place at any point up to 23:59:59 on the specified day in order to be effective. Was Part 8 appropriate?The recent case of A&V Building Solutions Ltd v J&B Hopkins Ltd2 , together with the TCC Guide, sets out the factors to consider when deciding if a parallel Part 8 application is appropriate. In summary:
Elements relied on the case of Hutton Construction Limited v Wilson Properties (London) Ltd3 as authority for imposing an additional factor that there is a requirement that the point or points raised by way of Part 8 have to be shown to be “obviously wrong” The Court held that the case of Hutton did not impose a higher Part 8 “test” and the Court should be guided by the principles outlined in the bullet points above. The issue at hand was deemed to be ”short and straight-forward” and as such, when combined with the lack of challenge by FK of the evidence put forward by Elements, Part 8 proceedings were appropriate. Key take aways
[2] [2023] EWCA Civ 54 [3] [2017] EWHC 517 (TCC) Key contacts
Latest Insights
Latest News
Latest Eventsclient news June 02, 2026 Next stop, public ownership: Eversheds Sutherland advises DfT on GTR transi... firm news June 01, 2026 Shaping the Future firm news June 01, 2026 Eversheds Sutherland strengthens restructuring offering with senior partner... firm news June 01, 2026 Eversheds Sutherland strengthens Commercial Advisory practice with technolo... |