Can a settlement agreement be a construction contract?
August 08, 2025
Can a settlement agreement be a construction contract?August 08, 2025 Construction contracts are prone to emerging issues and disputes, and settlement agreements which aim to: (i) settle those matters and avoid proceedings; (ii) vary the contract’s operation; and/or, (iii) provide a ‘line in the sand’ or ‘reset’ for the contract’s delivery, are common-place. BackgroundRaise Now Ealing Ltd (“RNE”) appointed London Eco Homes Ltd (“LEH”) to carry out construction work under a JCT Intermediate Building Contract with contractor’s design (the “Contract”). The Contract contained an express right to refer disputes to adjudication, and was also subject to the Construction Act. Various issues arose, which were the subject of a settlement agreement. This settlement agreement contained a schedule of payments to be made by RNE to LEH. RNE failed to make payment in accordance with the schedule, so LEH made a referral to adjudication. RNE challenged the adjudicator’s jurisdiction on the basis that adjudication did not apply to the settlement agreement. The adjudicator rejected this challenge and decided in LEH’s favour, ordering RNE to pay the outstanding settlement sum and his fees. RNE failed to pay in accordance with the adjudicator’s decision and LEH sought to enforce the decision by summary judgment. What did the settlement agreement say?The relevant clauses were as follows:
There was no express provision for adjudication. What were the parties' positions?RNE argued that the settlement agreement was a free-standing agreement, which contained an entire agreement clause and it was intended to supersede and replace the original contract. The effect of the settlement was to terminate the Contract, so it could not confer jurisdiction on the adjudicator. It also highlighted that there was no ADR clause written into the settlement agreement, but that there was an exclusive jurisdiction clause submitting to the authority of the courts of England and Wales. What did the court decide?As RNE conceded that sums were due pursuant to the settlement agreement, the only issue before the Court was whether the adjudicator had jurisdiction to determine the dispute. This turned on whether there was an adjudication clause implied by statute or, alternatively, whether the adjudication clauses in the Contract survived for the purposes of the dispute that was referred to the adjudicator. 1. The settlement agreement was a construction contract, thus engaging a statutory right to adjudicate at any time. 2. The Contract’s adjudication clauses applied to the settlement agreement because it was a variation of the Contract. The Court found that there were a number of reasons for construing the settlement agreement as a variation to the Contract. These included the settlement agreement’s:
As the dispute referred concerned RNE’s payment obligations, which ultimately related to sums payable under the Contract, the right to adjudicate had arisen pursuant to the Contract and LEH was therefore entitled to summary judgment. In reaching this decision, the Judge focused on whether or not the dispute was one that was “under” the Contract, which in turn meant that ADR could be used to settle the dispute. The Judge rejected the argument that the governing law and jurisdiction clauses meant that disputes had to be dealt with exclusively by the courts of England and Wales, and not ADR. Rather, these were standard provisions that made it clear that English law applied and that any dispute which reached the courts would be tried in the English Courts. This is in line with the current approach by the Courts which, in any event, had the power to order the parties to engage in ADR. Key takeawaysThis decision turned on whether or not the settlement agreement was connected to the Contract. Whilst this will depend on the specific facts and drafting, it is difficult to envisage circumstances where a settlement agreement is entirely unconnected to the underlying contract to which it relates. When drafting settlement agreements parties should therefore be aware that the dispute resolution clauses of the underlying agreement may prevail and express drafting may be required if this is not the parties’ intention. 1 [2025] EWHC 1505 (TCC) Latest Insights
Latest News
Latest Events
legal updates May 29, 2026 Consumer Lens - Session 1 | The Rise of European Class Actions podcasts and webcasts May 29, 2026 Tax NOLs in Cross-Border Structures Webinar legal updates May 28, 2026 EU Pay Transparency Directive legal updates May 27, 2026 Trade secrets and the Digital Omnibus: key risks and safeguards client news June 02, 2026 Next stop, public ownership: Eversheds Sutherland advises DfT on GTR transi... firm news June 01, 2026 Eversheds Sutherland strengthens restructuring offering with senior partner... firm news June 01, 2026 Eversheds Sutherland strengthens Commercial Advisory practice with technolo... client news May 28, 2026 Eversheds Sutherland advises Schroders Greencoat on acquisition of Dutch bi... virtual UK employment law training June 09, 2026 1pm - 4pm (BST) Virtual virtual Nordic (Denmark, Finland, Norway and Sweden) employment law training June 16, 2026 12.45pm - 4pm (BST) Virtual virtual Introduction to Swiss employment law June 23, 2026 2pm - 5pm (GMT) Virtual virtual UAE - Employment law in the Dubai International Financial Centre September 10, 2026 9.30am - 1.30pm (GMT) Virtual |